About the project:
Construction works for solid waste landfill for Nisporeni and surrounding localities, designed on the area outside of Nisporeni.
The main tasks of TCD team within the project were as follows:
- Interacting with the project team, engineers, and designers involved in the process. Given the designs for construction, TCD team supervised the planning, scheduling, and implementation of those designs;
- Preparation of construction progress reports;
- Monitoring the activities of subcontractors to ensure compliance with design, specifications and procedures, statutory regulations, compliance with national construction standards;
- Supervision of construction activities to ensure personnel and environmental safety, anticipate potential problem areas, analyse and recommend solutions or corrective actions;
- Keeping Regional Development Agency management informed of project status, highlighting deviations from the established plan, if necessary.